The trades have been in doing punch list items.
The Powder Room vanity cabinet doors were changed out and are now correct. Many of the kitchen cabinet items were addressed. The trash compactor was leveled.
The painters were doing the painting around the windows along with various touch up items. Our builder said he met with the lanai / front porch flooring company this afternoon and they would be doing touch up on their items this week.
The Pringle internal Quality Assurance review is scheduled for tomorrow. That's when they have three or four Pringle people walk through and critique the fit and finish of the home in preparation for the customer walkthrough a week later.
We're now down to less than two weeks to closing.