I'm still in Michigan, so don't know what actual progress was made on the home. However, TBCI, my private inspection service had done their pre-drywall inspection on Thursday and found 18 items incomplete. One of those is ok, as I had agreed with the speaker wire installer that his recommended location was better than the one I had chosen.
However, I'm somewhat chagrined to learn that I had missed 16 of the 17 other items he had found. That's why I am not a builder.
To help readers learn, here is the text of the items my inspector found still open before drywall should begin:
1. The eave drip is bent on the front of the garage and should be repaired.
2. A flush sill is installed in the window in the master bedroom which look out to the lanai. All of the sills
shown on the drawing are projected sills. This looks major to me.
3. Tubing for the pest defense system was not installed in all of the interior walls of the house. This is the
first time I have seen this [type of] installation in a Pringle home or any other.
4. Truss B9 was not constructed according to the engineered drawings present on the job site. The truss
manufacturer should provide a drawing and engineering for the truss installed.
5. Dead wood [wood for the ceiling drywall to be attached to] at the ceiling in the study at the wall common to the entry does not extend to the corner.
6. Dead wood at the ceiling in the master bedroom closet above the door is out of place and corrections are needed.
7. The 2x4s which support the distribution box for the air conditioning ducts in the bedroom hall project
below the ceiling line and should be cut flush with the bottom cord of the truss.
8. The ledge or shelf at the master bath tub is not framed at 30 inches aff (above finished floor) and only projects 4 1/2 inches
above the tub.
9. The attic access in the master bedroom is not framed in. The electrical contractor removed one of the
framing members to properly locate the light fixture.
10. The knee wall was not installed at the guest bath tub.
11. Extend the framing at the build out on the valve wall at the guest bath tub to the edge of the tub and
install backing for the drywall/wet wall transition on the opposite wall.
12. There is a gap in the draft blocking in the ceiling of the guest bath which should be sealed.
13. A nail plate is missing on a furring strip below the master bedroom window looking out to the lanai at
the corner to the right.
14. The wall mount speaker drop in the great room wall common to the kitchen is not located according to
the location on the drawings. I had previously agreed that this was a better location.
15. There is marking on the floor in the den to relocate a receptacle on the wall common to the lanai. This
has not been done.
16. Wind has blown out a piece of insulation in the wall common to the garage under the electrical panel
which should be re installed.
17. Nail plates are missing at the water supply lines in the master bath shower.
18. Bowed studs were observed in the laundry room, kitchen, nook, master bedroom hall to the bath, and
the master bath shower. These studs are marked with an X. There are 7 studs total.
Because my builder, Cliff, is on vacation, another builder, Steve Edmunsen, is working on the issues.
I've checked my project management plan and don't think this is a significant delay, if we can get all the issues fixed next week. I'm still looking at early November for a move in date.