As of this afternoon, the drywall was hung and the crew was starting on the taping and mudding. The rooms look a lot different with the drywall separating the rooms.
I met with my builder and he brought the electrical supervisor in to discuss a missing smoke detector and the need to align one of the ceiling lights in the kitchen.
He will also get an attic access that was just covered over with drywall cut open.
We discussed plans for the next few weeks. It looks as though we are still on schedule for an early November completion, and for sure by Thanksgiving, unless we get bad hurricanes through the area.
Here are some pictures showing the stucco preparation and completion:
Here are some of the insulation work in progress, before cleanup: