Wednesday, August 8, 2007

Tub & Electricity





There was lots of activity today. Our Builder called about 10:30 this morning to advise of a problem with the guest bath tub. The model delivered was a drop in version, rather than one with a tile flange. We agreed that it would not work and that the correct model needed to be ordered. He said it would take about two weeks, and would cause a construction delay, as he could not get his plumbing inspection or all rough-in inspection until it was installed.

This afternoon he called to tell me that they were having expedited shipment of the replacement and that it is expected to be delivered next Tuesday. Good news!

The Master Bath tub was delivered and installed. The shower valve for the Master Shower was mounted, but not fully plumbed.

HVAC ductwork minor problems were fixed, and inspection is scheduled.

Our main electrical service was pulled and the meter was installed.

The Builder and I agreed to do the pre-drywall inspection next Tuesday.