Friday, August 3, 2007

HV Electrical

There was lots of activity today. The electrical crew was there with five or six electricians running wires, installing ceiling light boxes, etc. My Builder, the Electrical Crew Supervisor, and I discussed and, hopefully, resolved the issues regarding the disconnect box for the hot tub on the rear of the house near the lanai.

There was a small problem in the front study, as the boxes for the recessed lights could not be located where I had specified them due to trusses in the way. We agreed on a new location.

The roofers were out early and finished the shingles, including the various vents and furnace chimney. Now I'll hope for a good, steady rain before the dry wall goes in, so I can see if there are any leaks.

Some crew had installed Tyvek covering over any of the wood areas outside (e.g. at the front porch areas around the curved windows.

During my weekly Builder discussion, I found that there is a delay on our two bathtubs. They should have been in two weeks ago. The Builder has elevated the issue to his supervisor. The plumbers will finish their rough-in when the tubs arrive and are installed.

A temporary, wrong color window will be installed in the garage to allow for inspection, and then will be changed when the correct one arrives.

I'll try to get pictures this weekend and post some.