On Thursday, the HVAC installer continued installing duct work. There is a lot of connection and sealing done, working 13' above floor level in the spaces between the trusses. He expected to be done by the end of the day. He also had cut all the holes in the roof for the four bathroom exhaust vents, the furnace chimney, and the dryer vent.
Because it was raining steadily, the roofers decided to leave. Hopefully on Friday they will return and put the vents in at all the new holes in the roof.
We had to postpone our meeting with the landscape contractor as Judi had a terrible migraine, and I, as a husband, am not qualified to make decisions on plant color and placement. ;)
The framers came and furred out the wall in the utility room by 1/2", as there was not enough room in the 3 1/2" wall to run the dryer duct work. The framers, Builder, and I had all missed that item, as it was specified as being a 6" wall on the prints.
No electricians yet.
Thursday, August 2, 2007
Subscribe to: