Today the plumbing crew worked on the rough-ins. They installed the gas connection point beside the house, ran the gas lines to the furnace location and the gas dryer location, and ran the gas line for the future standby gas generator. They also did most of the plumbing rough-in. They still have to install the master bath shower valve plumbing, after the lines are moved to the right location, as well as the refrigerator ice maker line and the washer hot and cold water lines.
The framers corrected the issue with the Great Room slider stacking location and cleaned up the wood pile from the back of the lanai.
The dumpsters were all emptied again. That's it for today.