As indicated earlier, our slab was poured on Thursday morning, 6/28. That afternoon, they did some of the saw cuts in the concrete, to encourage it to crack in specific areas. On Friday morning they did the rest of the saw cuts and did a rough grade for about eight feet around the slab. I picked up a lot of the nails from the forms, just to avoid finding them next year when I am working in the garden.
The slab is now in the "curing" stage. Our Builder told me he expects the cement blocks to be staged on 7/03 and that the block masonry crew will start work on 7/6. Basically we are in a "wait" stage for the next week.
Also, on Thursday, I got the final plan page for the HVAC system. We've been going back and forth with Design to be sure that the plans correctly showed the HVAC zoning system we want. We also got a no charge change order to sign and return indicating that this is the system we do want.