Today the exterior concrete flatwork was done. The driveway, sidewalk by the street, sidewalk to the front door, floor for the cage, and the various pads (e.g. A/C Compressor, exit from the cage) were poured in the morning. By mid-day they were finished working them and had covered them all with large sheets of plastic to protect against the afternoon rains.
The tile crew was continuing their work. In areas where the floor tile had been grouted, they had installed covering brown "butcher" paper to protect the floor. They were working on the tile for the tubs and shower.
The next steps on the critical path are cabinet install, then countertops, then HVAC (furnace / AC coil & compressor) install and startup.
Today I also obtained Homeowners Insurance coverage effective just before my projected close date.
Tuesday, September 18, 2007