Friday a tile crew started work. They scraped the slab to clean up the residue left from the drywall, put down "red guard" around all the saw cuts in the slab, and stacked all the boxes of tile on the rear lanai. By Friday evening they had placed, but not cemented, two long rows of tile from the front Study all the way though the Great Room and through the Nook. Since we are having tile laid on the diagonal, this is the longest contiguous run of tile.
The outside concrete flatwork for the driveway, walks, and cage was not poured. A crew came by and adjusted the forming for one pad that was off a bit, and the supervisor said they would probably pour late Monday morning.
Our Builder discussed plans for next week with us and agreed that my projection for closing of between November 5 and November 10 was looking like a good estimate. Of course, there were no commitments to a firm date, as there is a lot of hurricane season left between now and then.