The tile crew finished up the tile installation today, except that there is no shower drain in the master shower. They tiled over it, so it will have to be cut out. Not a big problem.
The cabinet installation team was busily at work installing the cabinets. There are a few issues that I'll have to discuss with my builder on Friday. Most look fine.
The door from the laundry room to the garage is not where we expected it to be. This causes a problem as we had planned to put our "extra" refrigerator in the laundry room and it will stick out 3" in front of the door. This is likely my fault, as I did not get the exact dimensions for the door location spelled out on the print. From the location shown, if you scale the dimensions, it is wrong, but without exact dimensions, the framers field locate things.
We met with our builder about this and agreed to downsize the door from 3' 0' to 2' 8" to gain the 4" needed. This avoids a major redo of a load bearing wall.
The Pringle photographer was out to take new pictures, so there should be some on the picture site tomorrow.