Good progress was made last week. The critical path, or the items that are now controlling the closing date seem to be:
- replacement kitchen cabinets for those that are wrong. If they have to be ordered, there is a three week lead time.
- irrigation system installation and inspection,
- landscaping, which is pending a meeting with the City of Mount Dora,
- a lot of city final inspections for plumbing, electricity, sewer, gas, landscaping, etc.
- final Certificate of Occupancy
We'll see what happens this week. While the Critical Path says that we could be done by the end of the month, if everything goes just right, I'm now beginning to think that even the week of November 5th is optimistic, and that the week of November 12th is more likely.
During the last few days we've been concentrating on a lot of soon after close items we want done, such as the garage floor treatment, blinds, screening of the front porch, etc.
The next few weeks will be busy.