Friday, October 12, 2007

Misc. Work

The shut off valves for the gas line for the gas clothes dryer and the stub out line to the future generator were installed. The gas line was connected to the water heater. Now the gas meter needs to be installed.

The shelving in the Master Bedroom Closet has been corrected.

An almost-final grade has been done on the lot in the rear, sides, and part of the front. More dirt is needed and more raking to get the stones / junk out of the dirt to get to a final grade.

The painters were working on the inside doing the caulking of the baseboards. Actually, when I went in at about 2:30 PM, the three painters were lying down resting in the Great Room. A few minutes later they were back working.

The critical path for completion is now Florida Designer Cabinets correcting the cabinet errors. If, big IF, they get their act together, we may be able to close by Thanksgiving, otherwise we're potentially into December. I called the cabinet manufacturer, Wellborn, yesterday and have some potential solutions, but don't know if FDC will go that route.

No comments: