We're back from vacation. While we were gone the counter tops were installed, along with all the room door handles / locks. Also the HVAC compressor, coil, furnace, and thermostats were all installed. No electrical connections were made and I was told today that the electricians, not the HVAC people will do all that hook up. Then HVAC comes back to program / tune the system.
We got a surprise on the countertops in the bathrooms. They were not the same color as the kitchen, as we had expected, but were a more neutral color. This is, I believe, our mistake, as I went back and checked the individual decor change order and the kitchen and bathroom countertop colors are different. We got what was on the change order that we signed. It's not a bad color and we'll live with it, rather than spend about $2500 to change it.
All the electrical fixtures are in boxes in the Master Closet.