Wednesday, October 17, 2007

LV Trim & Flatwork Painting

The LV trim was partially done today. Cable outlets were installed, along with telephone. The Ethernet outlets were missed, either just covered with a blank, or a smaller telephone jack installed instead of the Ethernet outlet. None of the terminations at the panel were done. Our builder called the subcontractor and said she was having problems with her installers.

The rest of the front porch and lanai painting was done. They will still have touch up to do, but there was some progress.

Out builder said that the replacement kitchen cabinets are being expedited, and should arrive by the end of the month.