Today a crew cleaned the lanai and front porch concrete and applied the "knock down" texture. I expect it will be painted next week.
I spent an hour or so doing a detailed review of the kitchen cabinets versus the plans. There are lots of differences. It appears that the plans either didn't get to Florida Designer Cabinets, or they thought it was just a suggestion. I guess it's time to meet with Cliff on Monday.
I also walked through all the other rooms and updated my punch list. There are lots of minor issues that I expect would be corrected in the drywall / paint / electrical final reviews, even if I didn't note them. This is normal. I also found a few medium level issues including one window that seems to have a broken lift mechanism. This early punch list will, I believe, make it easier for us at the "final" walkthrough. Otherwise I think it would be overwhelming to check everything to be sure it is right.
Saturday, October 6, 2007